$28 per MWh. Energized ahead of the queue.

Teton Digital develops vertically integrated power generation and Tier-compatible data center campuses across Alberta and the United States. We bring our own power onto our own sites — and deliver capacity two to five years ahead of grid-dependent alternatives.

THE MACRO PROBLEM

Power, not silicon, is the binding constraint on AI.

New grid interconnections in major U.S. hubs now take four to seven years. The interconnection queue stands at roughly 1,500 gigawatts. Hyperscalers and AI operators are increasingly committing capital to dedicated, behind-the-meter generation because the alternative is waiting for a grid that cannot move at the pace of compute demand.

1,500 GW

U.S. grid interconnection queue backlog

Source: Lawrence Berkeley National Lab / U.S. DOE, 2025

4–7 yrs

Wait time for new grid connections in major U.S. hubs

Source: LBNL / DOE, 2025

$800B+

Expected 2026 AI infrastructure, compute, and data center capex

Source: Morgan Stanley Research

+165%

Data center power demand growth through 2030

Source: Goldman Sachs Research

What we do

Three structural advantages.
Built together, by design.

01 — Economics

Lowest power economics in North America

Teton's flagship project delivers all-in cash cost of power at approximately $28 per MWh — roughly a quarter of the all-in delivered cost in major U.S. data center markets, and approximately $300M+ in annualized OPEX savings per 500 MW deployed versus a Virginia-equivalent site.

~$28/MWh

all-in, Year-1 cash

02 — Speed

Years ahead of the queue

We bring our own power onto our own sites, which lets us energize compute capacity two to five years ahead of grid-dependent alternatives. Our flagship Alberta project is permitted and tracking to Q3 2028 — two to three years ahead of every other Alberta power and data center project in the queue.

2–5 yrs

faster than grid-dependent

03 — Integration

Vertically integrated

Power and campus are developed together — generation, interconnection, fiber, water, and Tier-compatible data hall pads on one site, under one sponsor. From land acquisition through operations, we own the full lifecycle.

One site.

One sponsor.

The $28 per MWh story

Power at $28 per MWh.

Teton sites projects where natural gas is structurally cheap, where the climate reduces cooling load, and where regulators are actively incentivizing new dispatchable generation.

AECO-hub natural gas has historically traded approximately 40% below NYMEX / Henry Hub. The Alberta climate reduces cooling load and improves PUE to below 1.25 versus 1.35–1.41 in major southern U.S. markets. Alberta levies zero tariffs on imported compute equipment.

The result is all-in cash cost of power that no U.S.-sited builder can match — with the savings to match.
Virginia Texas Alberta (Teton)
All-in delivered power ($/MWh) ~$105 ~$50 ~$28
Average PUE 1.35 1.41 <1.25
Tariffs on compute equipment Variable Variable None
Interconnection queue (typical) 4–7 yrs 3–5 yrs Direct path, Behind the Meter

Alberta figure: Year-1 (2028) cash cost of power for Black Bear on a behind-the-meter delivery basis. Buildup: fuel + variable O&M / LTSA + maintenance reserve + net TIER carbon + fixed SG&A. Source: Black Bear project financial model. Virginia and Texas figures sourced to PJM and EIA STEO 2026 forecast. Annualized OPEX savings = (Virginia $/MWh − Alberta $/MWh) × 500 MW × 8,760 hours × 90% capacity factor. Excludes capital recovery and equity return.

~$300M+

in annualized OPEX savings per 500 MW deployed in Alberta versus a Virginia-equivalent site.

Flagship projects

Two flagship Alberta projects.
3 GW+ pipeline.

First power energizes this year. Northern Forge Phase I (30 MW) comes online Q4 2026, with subsequent capacity additions through 2027. Black Bear (466 MW) energizes Q3 2028 with a defined pathway to ~3 GW across the campus. Additional U.S. pipeline spans North Dakota, Iowa, and Texas. Scale across three years — 2026, 2027, 2028.

Black Bear
Alberta, Canada
View campus page →
Scale

466 MW NGCC + ~2,500-acre Tier-compatible campus, ~3 GW pathway.

Status

Ready to build. Fully permitted federally, provincially, and at the Indigenous level. AESO Cluster 3 filed.

Energization

Q3 2028

All-in power cost

~$28/MWh Year-1 cash basis

Northern Forge
Alberta, Canada
View campus page →
Scale

125 MW behind-the-meter gas-to-compute campus.

Status

Permits largely in hand. 10-year firm gas supply. Dedicated 6-inch pipeline for the full 125 MW build.

Energization

Phase I (30 MW) Q4 2026

All-in power cost

<$30/MWh long-term

Additional U.S. pipeline
  • North Dakota100 MW Tier 3 campus. Conditional Use Permit secured for Phase II.
  • Iowa50+ MW behind-the-meter solar + gas hybrid. 10-yr fixed PPA at ~$40/MWh.
  • Texas256 MW behind-the-meter. ERCOT interconnect approved. 15-yr fixed at ~$35/MWh.

View full pipeline →

Press & updates

News.

Press May 2026

Teton Digital Gets Go-Ahead for 100MW Data Center in North Dakota

Data Center Dynamics covers Phase II conditional use permit approval for Teton's North Dakota campus.

Read on DCD →
Project milestone Q4 2026

Northern Forge Phase I energization

Anticipated milestone — first power from the 30 MW Phase I behind-the-meter site.

Project milestone Aug 2026

AESO Cluster 3 progress

Anticipated milestone — Black Bear Cluster 3 interconnection process step.

What We Do:

  • Data Center Development

    Building data centers from the ground up. We build data centers that are strategically located to maximize operational efficiencies and long-term business stability.

  • Vertically Integrated Power Generation

    Creating reliable and cost-effective data centers in any environment.

  • Data Center Services

    Whether you need help building your own data center, optimizing your energy assets, or need colocation services Teton Digital can help.